S-II

S-II
The Apollo 6 S-II stage during stacking operations in the VAB
ManufacturerNorth American
Country of originUSA
Used on
General characteristics
Height24.9 m (82 ft)
Diameter10 m (33 ft)
Gross mass480,000 kg (1,058,000 lb)
Propellant mass443,000 kg (977,000 lb)
Empty mass36,200 kg (79,700 lb)
Launch history
StatusRetired
Total launches13
Successes
(stage only)
12
OtherPartial failure (Apollo 6)
First flightNovember 9, 1967 (AS-501) Apollo 4
Last flightMay 14, 1973 (AS-513) Skylab 1
Rocketdyne J-2
Powered by5
Maximum thrust4,400 kN (1,000,000 lbf)
Specific impulse421 seconds (4.13 km/s)
Burn time367 s
PropellantLH2 / LOX

The S-II (pronounced "S-two") was the second stage of the Saturn V rocket. It was built by North American Aviation. Using liquid hydrogen (LH2) and liquid oxygen (LOX) it had five J-2 engines in a quincunx pattern. The second stage accelerated the Saturn V through the upper atmosphere with 1,000,000 pounds-force (4.4 MN) of thrust.

History

S-II assembly building in Seal Beach, CA

The beginning of the S-II came in December 1959 when a committee recommended the design and construction of a high-thrust, liquid hydrogen fueled engine. The contract for this engine was given to Rocketdyne and it would be later called the J-2. At the same time the S-II stage design began to take shape. Initially it was to have four J-2 engines and be 74 feet (23 m) in length and 260 inches (6.6 m) in diameter.

In 1961 the Marshall Space Flight Center began the process to find the contractor to build the stage. Out of the 30 aerospace companies invited to a conference where the initial requirements were laid out, only seven submitted proposals a month later. Three of these were eliminated after their proposals had been investigated. However it was then decided that the initial specifications for the entire rocket were too small and so it was decided to increase the size of the stages used. This raised difficulties for the four remaining companies as NASA had still not yet decided on various aspects of the stage including size, and the upper stages that would be placed on top.

On September 11, 1961, the contract was awarded to North American Aviation (who were also awarded the contract for the Apollo Command/Service Module), with the manufacturing plant built by the government at Seal Beach, California.[1] 15 flight stages were to be produced.

Plans were also developed to build 10 follow-on stages, S-II-16 through -25, but funding to assemble them never materialized.[2] These stages would have supported later Apollo missions, including those of the Apollo Applications Program.

Configuration

Cutaway illustration of the S-II (second) stage

When fully loaded with propellant, the S-II had a mass of about 480 t (1,060,000 lb). The hardware was only 7.6% of this—92.4% was liquid hydrogen and liquid oxygen.[3]

At the bottom was the thrust structure supporting five J-2 engines in a quincunx arrangement. The center engine was fixed, while the other four were gimballed, similar to the engines on the S-IC stage below.

Instead of using an intertank (empty container between tanks) like the S-IC, the S-II used a common bulkhead (similar to that of the S-IV and S-IVB stages) that included both the top of the LOX tank and bottom of the LH2 tank. It consisted of two aluminum sheets separated by a honeycomb structure made of phenolic resin. It insulated a 126 °F (70 °C) temperature differential between the two tanks. The use of a common bulkhead saved 3.6 tonnes in weight, both by eliminating one bulkhead and by reducing the overall length of the stage. The S-II's common bulkhead design was tested in 1965 on the subscale Common Bulkhead Test Tank (CBTT), made of only 2 LH2 tank cylinders.[4]

The LOX tank was an ellipsoidal container of 10 meters diameter and 6.7 meters high holding up to 83,000 US gallons (310 m3) or 789,000 pounds (358 t) of oxidizer.[5] It was formed by welding 12 gores (large triangular sections) and two circular pieces for the top and bottom. The gores were shaped by positioning in a 211,000-liter tank of water with three carefully orchestrated sets of underwater explosions to shape each gore.

The LH2 tank was constructed of six cylinders: five were 2.4 meters high and the sixth was 0.69 meters high. The biggest challenge was the insulation. Liquid hydrogen must be kept colder than about 20 °C above absolute zero (−423 °F or 20.4 K or −252.8 °C) so good insulation is very important. Initial attempts did not work well: there were bonding issues and air pockets. Initially, the stage was insulated with a honeycomb material. These panels had grooves milled in the back which were purged with helium during filling. The final method was to spray insulation on by hand and trim the excess. This change saved both weight and time and avoided the issues with air pockets entirely. The LH2 tank volume was 260,000 US gallons (980 m3) for storing 153,000 pounds (69 t) of liquid hydrogen.

The S-II was constructed vertically to aid welding and keep the large circular sections in the correct shape.

Stages built

Serial number Use Launch date Current location Notes
Common Bulkhead Test Tank (CBTT) Demonstrated S-II's common bulkhead on a subscale tank Unknown Subscale S-II tank assembly composed of two LH2 tank cylinders, a standard forward bulkhead, common dome, and aft skirt with a modified aft bulkhead. Tested in 1965.[4]
S-II-F Used as Dynamic Test Stage replacement after destruction of S-II-S/D and S-II-T At the U.S. Space & Rocket Center, Huntsville, Alabama
34°42′38″N 86°39′26″W / 34.710544°N 86.657185°W / 34.710544; -86.657185 (S-II-F)
Completed facilities checkouts and propellant load tests at Kennedy Space Center in 1966 as part of the SA-500F stack.[6]
S-II-T "All-systems" test vehicle for engine firings First all-up S-II stage, assembled between 1963 and 1965. Completed several engine tests at the Mississippi Test Facility (now the Stennis Space Center). Destroyed by accidental LH2 tank overpressurization during pressure testing May 28, 1966[7][6]
S-II-D Dynamic test vehicle Assembly canceled in 1965 to prioritize work on the first flight stage, S-II-1. Testing requirements transferred to S-II-S, which was renamed S-II-S/D.[6]
S-II-S/D Structural and Dynamic Test Vehicle Destroyed in test stand September 29, 1965
S-II-1 Apollo 4 November 9, 1967 32°12′N 39°40′W / 32.200°N 39.667°W / 32.200; -39.667 (S-II-1)[citation needed] Carried "Camera Targets" spaced around the forward skirt and carried cameras to record first stage separation
S-II-2 Apollo 6 April 4, 1968 Carried cameras to record first stage separation, similar to Apollo 4. Two engines failed during ascent due to pogo oscillation and incorrect engine control wiring.
S-II-3 Apollo 8 December 21, 1968 31°50′N 38°0′W / 31.833°N 38.000°W / 31.833; -38.000 (S-II-3)[citation needed]
S-II-4 Apollo 9 March 3, 1969 31°28′N 34°2′W / 31.467°N 34.033°W / 31.467; -34.033 (S-II-4)[citation needed] 1800 kg lighter allowing 600 kg more payload, more powerful engines and carried more LOX
S-II-5 Apollo 10 May 18, 1969 31°31′N 34°31′W / 31.517°N 34.517°W / 31.517; -34.517 (S-II-5)[citation needed]
S-II-6 Apollo 11 July 16, 1969 31°32′N 34°51′W / 31.533°N 34.850°W / 31.533; -34.850 (S-II-6)[citation needed]
S-II-7 Apollo 12 November 14, 1969 31°28′N 34°13′W / 31.467°N 34.217°W / 31.467; -34.217 (S-II-7)[citation needed]
S-II-8 Apollo 13 April 11, 1970 32°19′N 33°17′W / 32.317°N 33.283°W / 32.317; -33.283 (S-II-8)[citation needed] Inboard engine failed during ascent due to pogo oscillation.
S-II-9 Apollo 14 January 31, 1971
S-II-10 Apollo 15 July 26, 1971
S-II-11 Apollo 16 April 16, 1972
S-II-12 Apollo 17 December 7, 1972
S-II-13 Skylab 1 May 14, 1973 34°00′N 19°00′W / 34.000°N 19.000°W / 34.000; -19.000 (S-II-13)[citation needed] Modified to act as the terminal stage. The only S-II to enter earth orbit, made an uncontrolled reentry into the Atlantic on January 11, 1975.[8] Interstage failed to separate due to payload damage during launch.
S-II-14 Apollo 18 (cancelled) N/A Apollo-Saturn V Center, Kennedy Space Center
28°31′26″N 80°41′00″W / 28.52385°N 80.68345°W / 28.52385; -80.68345 (S-II-14)
From the cancelled Apollo 18 mission.[6]
S-II-15 Apollo 19, later Skylab 1 backup (not flown) N/A Johnson Space Center
29°33′15″N 95°05′39″W / 29.554051°N 95.094266°W / 29.554051; -95.094266 (S-II-15)
From SA-515 the Skylab backup vehicle which NASA did not use. Also earmarked for Apollo 19.[6]

See also

References

  1. ^ Aikens, David. "Saturn Illustrated Chronology - Part 2: January 1961 through December 1961". NASA-Marshall Space Flight Center. p. 28.
  2. ^ "Manufacturing plan for Saturn S-II, Stages 16-25". uah.edu. Retrieved 2023-03-18.
  3. ^ Apollo 18-19 Ground Ignition Weights (NASA)
  4. ^ a b "The Tortoise Steps of Saturn S-II". Retrieved 2023-03-20.
  5. ^ "Second Stage Fact Sheet" (PDF). Archived from the original (PDF) on 2015-03-26. Retrieved 2014-09-23.
  6. ^ a b c d e Kyle, Ed. "Saturn Vehicle History". spacelaunchreport.com. Archived from the original on March 21, 2022.
  7. ^ Aikens, David. "Saturn Illustrated Chronology - Part 7: January 1966 through December 1966". NASA-Marshall Space Flight Center. Retrieved February 17, 2011.
  8. ^ "Skylab rocket debris falls in Indian Ocean". Chicago Tribune. January 11, 1975. Retrieved October 22, 2014.
  • Bilstein, Roger E. (1980). Stages to Saturn: A Technological History of the Apollo/Saturn Launch Vehicles. NASA History Series SP-4206. NASA.
  • Apollo Saturn Reference Page
Retrieved from "https://en.wikipedia.org/w/index.php?title=S-II&oldid=1199754509"