Liddell Power Station

Liddell Power Station
Liddell Power Station in 2006
Map
Country
  • Australia
Locationnear Muswellbrook, New South Wales
Coordinates32°22′19″S 150°58′38″E / 32.37194°S 150.97722°E / -32.37194; 150.97722
StatusDecommissioned
Commission date1971–1973
Decommission date28 April 2023[1]
Owner(s)AGL Energy
Thermal power station
Primary fuelCoal
Secondary fuelOil
Turbine technologySteam turbine;
Gas turbine
Cooling sourceLake Liddell
Power generation
Make and modelEnglish Electric Company
Units decommissioned4 × 500 megawatts (670,000 hp)
2 × 25 megawatts (34,000 hp)
1 × 0.85 megawatts (1,140 hp) mini-hydro
Nameplate capacity2051 MW
Capacity factor51.02% (average 2017–2021)
Annual net output8,938 GW·h (average 2017–2021)
External links
CommonsRelated media on Commons

Liddell Power Station is a decommissioned coal-fired thermal power station that had four 500 megawatts (670,000 hp) EE steam-driven turbine alternators, providing a combined electrical capacity of 2,000 megawatts (2,700,000 hp).

Its operating capacity was assessed at 1,680 megawatts (2,250,000 hp) in April 2018.[2] Commissioned between 1971 and 1973, the station is located adjacent to Lake Liddell, near Muswellbrook in the Hunter Valley of Australia.

Unit 3 was taken out of service on 1 April 2022. Subsequently, Unit 4 was decommissioned on 24 April 2023, followed by Unit 2 on 26 April 2023. The last unit, Unit 1, was removed from service on 28 April 2023.

History

In September 1964, the Government of New South Wales announced its intention to construct the Liddell Power Station adjacent to Lake Liddell.[3] The first of four generators was completed in 1971, two more in 1972, and the fourth in 1973. At the time of completion, Liddell was the most powerful generating station in Australia. It was also the first major power station in New South Wales to be built inland, using fresh water for cooling instead of the more abundant saltwater used in coastal power stations. To accommodate this change, Lake Liddell was expanded to provide more water, requiring an 11-kilometre section of the Main Northern railway line to be rebuilt on a new alignment.[4][5] The completion of Liddell aided in the retirement of power stations in Sydney, such as Balmain and Bunnerong.

Originally, the plant was fitted with the then-standard electrostatic precipitators for dust collection, and the more efficient fabric filters (similar to those used at Eraring, Munmorah units 3 and 4, Vales Point 5+6, Bayswater, and Mount Piper) were retrofitted in the early 1990s, reducing particulate emissions to a barely visible level. Much of the coal was supplied by overland conveyors from mines it shared with the nearby Bayswater Power Station.

In 2007, a project commenced at Liddell to replace some of the station's boiler feed-water with hot water from a solar thermal array.[6] By March 2007, the project had reached a second-stage prototype but had not been connected to the power station. Subsequently, the 9 MW solar section was added to the Liddell coal-fired generator, but it has now effectively been closed. Analysts say that the incentive to use the solar boost was reduced by the removal of the carbon price and excess coal supply.[7]

Liddell Power Station was owned by the Electricity Commission of New South Wales, with ownership transferred to Macquarie Generation in 1996.[8] In September 2014, Liddell was included in the sale of Macquarie Generation by the New South Wales government to AGL Energy.[9]

Alternative fuel sources

In addition to the coal-fired steam turbines, Liddell Power Station also operates two GEC 25 MW oil-fired gas turbines[10] and a 0.85 MW mini-hydroelectric generator.[10][11] The power station is also "licensed to co-fire plant biomass and coal to produce electricity," allowing it to utilize sawdust and wood shavings from the nearby timber industry as a portion of its fuel, replacing up to 5% of its coal requirements.[12][13] However, in practice, biomass accounts for only about 0.5% of Liddell's total output.[citation needed]

Greenhouse emissions

According to estimates from Carbon Monitoring for Action, Liddell Power Station emits approximately 14.70 million tonnes of greenhouse gases annually due to burning coal.[14] In 2010, the Australian Government introduced a Carbon Pollution Reduction Scheme to combat climate change. This scheme has had an impact on emissions from power stations. The National Pollutant Inventory provides details of various pollutant emissions, including carbon monoxide, which was estimated to be 1,000,000 kilograms (2,200,000 lb) for the year ending 30 June 2011.[15] A Freedom of Information request in 2018 revealed that Liddell is permitted to emit three times more nitrogen oxide than the amount allowed under best practice guidelines.[16]

Operations

The generation table uses eljmkt nemlog[17] to obtain generation values for each year. Records date back to 2011.

Liddell Power Station generation (MWh)
Year Total LD01 LD02 LD03 LD04
2011 8,298,580 2,505,649 2,005,141 938,923 2,848,867
2012 7,865,039 2,462,253 2,132,226 1,264,696 2,005,864
2013 6,919,912 2,202,551 1,307,724 2,957,380 452,257
2014 7,585,713 1,794,219 1,615,699 1,923,304 2,252,491
2015 8,561,448 814,969 2,468,106 2,306,802 2,971,571
2016 9,037,331 2,409,097 2,087,540 2,361,397 2,179,297
2017 8,212,654 1,884,395 1,333,847 2,619,564 2,374,848
2018 9,147,807 2,634,806 2,413,888 1,214,612 2,884,501
2019 10,789,224 2,825,008 2,710,277 3,057,329 2,196,610
2020 8,350,728 2,044,901 1,410,233 2,230,925 2,664,669
2021 8,189,336 2,139,589 2,245,543 1,570,906 2,233,298

Closure & Site rehabilitation

AGL announced in 2015 and reaffirmed in 2017 that it intends to close the Liddell Power Station in 2022.[18] The closure of this and other coal-burning power stations in Australia led the Prime Minister Malcolm Turnbull to seek advice from the Australian Energy Market Operator on extending the life of a number of them,[19] to head off anticipated future electricity shortages.[20] Turnbull said the government had been advised that if the Liddell plant were to close in 2022, there would be a 1000MW gap in base load, dispatchable power generation.[19] The Turnbull government asked AGL to keep Liddell open beyond 2022, or to sell the Liddell Power Plant to Alinta Energy.[21] In August 2019, AGL announced that three of the turbines would be able to be kept running until April 2023, to ensure reliable power supply to New South Wales during the 2022–23 summer.[22] In December 2018, a proposed upgrade to the Bayswater Power Station was approved to be completed around the same time as the proposed closure of Liddell. Both are owned by AGL Energy and consume coal from the same mine. The upgrade approval did not impose tighter air emission controls, however AGL claimed that the closure of Liddell would result in a net improvement in air quality.[23]

The demolition process is expected to commence in early 2024 and take approximately two years. Work will include removal of all main structures (boilers, chimneys, turbine houses, coal plant) and ancillary buildings, and levelling of the site using recovered crushed concrete. More than 90 per cent of the materials in the power station are expected to be recycled during demolition, including 70,000 tonnes of steel, more than the total weight of steel works for the Sydney Harbour Bridge. Critical infrastructure, such as transmission connections, will be retained to support the ongoing use of the site as an industrial energy hub, helping provide employment and essential economic activity for the region. Planning approval has already been granted for a 500MW/2GWh grid-scale battery.[24]

Unit 3 was removed from service on 1 April 2022. Unit 4 was removed from service on 24 April 2023. Unit 2 was removed from service on 26 April 2023. The last unit, Unit 1, was removed from service on 28 April 2023.[25][26] Since April 2022, Liddell has typically been generating 750 MW on average.[27]

There is a 200-hectare dam containing 39m tonnes of coal ash at the Liddell site, and heavy metals have leached into Lake Liddell. AGL has earmarked $1.5 billion for cleanup of the Liddell, Bayswater, Torrens Island and Loy Yang A sites.[27]

Future Land Use

In late March 2024, Anthony Albanese, the Australian Prime Minister at the time, unveiled a significant government initiative aimed at bolstering the nation's renewable energy sector. The announcement centered around a substantial investment of $1 billion to transform a designated site into a cutting-edge manufacturing hub for the Solar SunShot project. This initiative represents a strategic move towards fostering domestic production of solar panels, aligning with broader efforts to reduce carbon emissions and transition towards cleaner sources of energy. The Solar SunShot project, a pioneering endeavor in the realm of solar energy, aims to drive innovation and efficiency in solar panel technology. By establishing a dedicated manufacturing facility in Australia, the government seeks to not only stimulate economic growth but also to position the country as a leader in renewable energy production and innovation on the global stage. Albanese's announcement underscores the government's commitment to addressing climate change and promoting sustainability through targeted investments in renewable energy infrastructure. Such initiatives are crucial for mitigating the environmental impact of traditional energy sources and advancing towards a more sustainable and resilient energy future. This strategic investment not only has the potential to create jobs and drive economic development but also signifies a significant step towards realizing Australia's renewable energy goals. It highlights the importance of proactive government policies and public-private partnerships in driving innovation and facilitating the transition to a greener, more sustainable energy landscape.[28]

See also

References

  1. ^ "Australia's oldest coal-fired station Liddell powers down in the Hunter Valley". ABC News. 27 April 2023. Retrieved 28 April 2023.
  2. ^ The fight about AGL's Liddell power station explained Australian Financial Review 9 April 2018
  3. ^ Power station to revive the coal industry Canberra Times 1 October 1964 page 27
  4. ^ Liddell Track Deviation Network July 1966 page 3
  5. ^ Seven-Mile Rail Deviation to Bypass Power Stn Project Railway Transportation October 1966 page 9
  6. ^ "Liddell Solar Project Update". Macquarie Generation. Retrieved 17 March 2007.
  7. ^ Giles Parkinson (21 March 2016). "CS Energy pulls the plug on the world's largest "solar booster" project". RE New Economy.
  8. ^ ""Macgen Website"".
  9. ^ "AGL completes the acquisition of Macquarie Generation assets". AGL Energy. 2 September 2014. Retrieved 16 January 2018.
  10. ^ a b "Statement of Corporate Intent 2005/2006" (PDF). Macquarie Generation. 13 December 2005. Archived from the original (PDF) on 19 August 2006. Retrieved 5 August 2006.
  11. ^ "Liddell Power Station" (Press release). Macquarie Generation. 7 February 2000. Archived from the original on 31 March 2006. Retrieved 5 August 2006.
  12. ^ "Renewable energy". Macquarie Generation. Archived from the original on 19 July 2006. Retrieved 5 August 2006.
  13. ^ "Biomass Co-firing". Macquarie Generation. Retrieved 5 August 2006.[dead link]
  14. ^ "Plant overview: Liddell". Carbon Monitoring for Action. 2007. Retrieved 7 June 2012.
  15. ^ "Liddell Power Station, Muswellbrook NSW". Carbon Monitoring for Action. Commonwealth of Australia: Department of Sustainability, Environment, Water, Population and Communities. 30 March 2012. Retrieved 7 June 2012.
  16. ^ "Liddell power station given special pollution exemption, documents reveal". ABC News. 22 May 2018. Retrieved 22 May 2018.
  17. ^ Nemlog
  18. ^ "AGL Energy statement on Liddell Power Station". AGL Energy. 6 September 2017. Retrieved 6 September 2017.
  19. ^ a b Osborne, Paul (6 September 2017). "Turnbull throws his weight behind coal power". InDaily. Retrieved 6 September 2017.
  20. ^ Hannam, Peter (7 September 2017). "Liddell power plant operating below 40 per cent capacity, faces 'mammoth' woes". The Age.
  21. ^ "Frydenberg pressures AGL to sell Liddell power station to Alinta". ABC News. 5 April 2018. Retrieved 22 May 2018.
  22. ^ Wakatama, Giselle; Farquhar, Liz (2 August 2019). "AGL defers Liddell, Torrens power plant closures in bid to avoid summer blackouts". ABC Newcastle. Retrieved 2 August 2019.
  23. ^ McCarthy, Joanne (8 December 2018). "Upper Hunter air quality will improve 'significantly' after Liddell closes, says Bayswater upgrade report". Newcastle Herald. Retrieved 8 December 2018.
  24. ^ "AGL appoints demolition contractor for Liddell as energy hub takes shape". AGL Energy. 18 January 2023. Retrieved 30 April 2023.
  25. ^ Doyle, Blake; Farquhar, Liz (1 April 2022). "Liddell power station wind-down begins after 50 years of burning coal". ABC News. Retrieved 13 April 2022.
  26. ^ "Australia's oldest running coal-fired power station is about to close. Are bills set to rise?". ABC News. 4 March 2023. Retrieved 5 March 2023.
  27. ^ a b Hannam, Peter (14 April 2023). "Turning out the lights: what is the legacy of the Liddell power station?". The Guardian.
  28. ^ "Anthony Albanese promises $1 billion to launch Australia solar panel production". ABC News. 27 March 2024. Retrieved 28 March 2024.

External links

Media related to Liddell Power Station at Wikimedia Commons

  • Proposed 38 MW solar thermal "coal saver" plant at Liddell
  • Solar thermal plant at the Liddell Power Station gets government support
Retrieved from "https://en.wikipedia.org/w/index.php?title=Liddell_Power_Station&oldid=1218107157"